Saturday, August 9, 2014

Weekly update





























Please welcome Mr Thierry (left) to the blog. His work was featured last summer, when he did the downstairs bathroom. He and Fabien (right) got started this week and made good progress. The upstairs, pink and black bathroom has been dismantled and the new bathroom is now framed.





















































Here's a little reminder of where it's starting from…

 

Patrick, our woodworker on last years bathroom and on this project will be doing the roof. The old, broken tiles will be thrown in a big wagon and delivered to an estate in Varenne where it will be used to fill pot-holes in farm roads. Patrick spent the week preparing but did not get started because it's been sooo rainy!